Malop Street Green Spine Works Update

Friday, 22 September 2017

Week of 25 September – Weekly Look Ahead

Yarra Street end of Malop Street

  • Continue installing strata vaults
  • Continue construction of new bike path
  • Pouring concrete footings for light poles
  • Planting of trees scheduled to commence on Tuesday 26 September
  • Continue installing electrical conduit for feature lighting
  • Pedestrian access to shop fronts will be maintained during works.

Moorabool Street end of Malop Street

  • Continue installing strata vaults
  • Continue construction of new bike path
  • Pouring concrete footings for light poles
  • Planting of trees scheduled to commence on Tuesday 26 September
  • Continue installing electrical conduit for feature lighting
  • Pedestrian access to shop fronts will be maintained during works.

Hours of work
Our work crews are working the following shifts next week in Malop Street, from Monday 25 September:

Split shifts between 6am – 10pm
Night works scheduled for 6pm – 6am Tuesday, Wednesday and Thursday
Please note Friday 29 September is a public holiday.